Plan to restore section of 7 Mile Bridge in Keys

MARATHON, Fla. (AP) — State and local officials have agreed to begin a program to conserve part of the historic Seven Mile Bridge in the Florida Keys.

The Monroe County Commission Wednesday approved a 30-year project to restore and maintain a 2.2-mile segment of the bridge between Marathon and Pigeon Key.

The span was built more than a century ago, when Henry Flagler constructed the Florida Keys Over-Sea Railroad.

In 1938 the bridge was converted for automobiles and in 1982 the Federal government built a new span. "Old 7" was retired and became a fishing pier and walking area, but the harsh marine environment has taken its toll.

Total conservation costs are about $77 million, with the Florida Department of Transportation paying 75 percent and the remaining funding coming from Keys governments.

©2014 by The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.